Problem definition
A modular and flexible process and systems concept was required for a research project. Metal foils needed to be coated with electrode material for the production of lithium-ion batteries. Aluminium or copper is used as the substrate, depending on whether cathodes or anodes are…
Latest News
from mk
Here you will find news about latest product innovations from the mk product portfolio and interesting application examples from the profile and conveyor technology and announcements around the company. In addition, news around the social and local commitment and the sustainability of Maschinenbau Kitz are available on LinkedIn or Facebook.
Problem definition
A process and a system for coating metal foils needed to be developed for a research and development project. The metal foils are used in the production of lithium-ion batteries. After coating, the foil must be dried before it can be calendered and rewound into a coil. The…
mk Technology Group, along with its parent company Maschinenbau Kitz in Troisdorf near Bonn in Germany, has taken over all shares in the Austrian company E-M-M-A GmbH, based in Wiener Neudorf near Vienna. The takeover has allowed the profile and conveyor technology specialist to add a highly…
At automatica 2018, the international trade fair for intelligent automation and robotics in Munich, conveyor technology specialist Maschinenbau Kitz will present its conveyor technology modules used for feeding and interlinking, as well as its innovative system solutions for transporting workpieces,…
Problem definition
In the production of longitudinal and cross beams, the production systems, the packaging robots and a station for manual tasks need to be interlinked. Positioning accuracy of +- 0.2 mm is required at the stations. Both longitudinal and cross beams are produced on the line, and the…
Problem definition
Two machining stations in a production process for cast parts need to be interlinked. The upstream and downstream machines have different cycle times. The interlink needs to restore the system’s autonomy. Two different types are produced on the line simultaneously. They are…
Problem definition
In the production of titanium screws, a handling solution needs to lift the baskets containing the screws from the main conveyor life to the buffer conveyor or tip the containers into a funnel. The solution needs to process different screw types in no particular order and be able…
Problem definition
During the production of titanium screws, the screws are expelled from the lathes and fill baskets made from perforated VA steel sheets. The screws that fall into the basket need to be counted. A lifting unit is also needed to transport the baskets to the main conveyor line at a…
Problem definition
In the production of titanium screws, baskets for holding the screws need to be conveyed from five lathes to the next transfer location. The conveying path needs to be adapted to the given spatial constraints. The lathes have a cycle time of 30 minutes per basket. During this…
Problem definition
Unpackaged granules need to be transported in a food production application. The conveyor technology needs to provide constant transport in a straight line; there are no requirements regarding the position or orientation of the product being conveyed. The system is part of the…